project scheduling with fuzzy number using simulated annealing algorithm

Clicks: 225
ID: 226158
2015
Article Quality & Performance Metrics
Overall Quality Improving Quality
0.0 /100
Combines engagement data with AI-assessed academic quality
AI Quality Assessment
Not analyzed
Abstract
This research studies resource constrained project scheduling problem in a part of a refinery construction project in real world. In real world, most of the activities are new and we have problems such as activity duration uncertainty. This problem causes a change in a project makespan. The RCPSP is NP-hard. Hence, we proposed an optimization method based on simulated annealing to solve the RCPS Problem. In this paper, Fuzzy sets theory is used to represent this activity duration uncertainty. Used schedule generation scheme, in the proposed simulated annealing algorithm, is a fuzzy parallel scheduling generation method. Proposed algorithm generates the minimum project makespan while considers renewable resource-constrained and activity precedence and also has ability to perform with fuzzy numbers for presenting project details such as start and final time of activities and project whole time with fuzzy numbers. Finally, the results of the algorithm will be evaluated and it will be represented that the proposed algorithm is very efficient and can be used by managers and scheduling programmers in real projects.
Reference Key
daneshpayeh2015journalproject Use this key to autocite in the manuscript while using SciMatic Manuscript Manager or Thesis Manager
Authors ;Hamzeh Daneshpayeh;Hossein-Ali Hassan-Pour;Mohamad Amirkhan
Journal molbank
Year 2015
DOI
DOI not found
URL
Keywords

Citations

No citations found. To add a citation, contact the admin at info@scimatic.org

No comments yet. Be the first to comment on this article.