A Forecast Model for the Level of Engineering Maturity Impact on Contractor’s Procurement and Construction Costs for Offshore EPC Megaprojects

Clicks: 114
ID: 102534
2019
Article Quality & Performance Metrics
Overall Quality
Not rated
Combines reader engagement with the AI quality analysis. This article has not been analysed, so there is no overall score — reader engagement is measured and shown alongside.
AI Quality Assessment
Not analyzed
Readership in this journal
Steady

Ranked #209 of 220 articles by views in energies

Most read Least read

Bar heights use a square-root scale. Only the 120 most-read articles are drawn; the journal has 220 in total.

Mint this article as an NFT
Not yet minted

Create a permanent, verifiable on-chain record of this article on the Scimatic Network. The NFT is held in your Journament account, and you can withdraw it to your own wallet at any time.

5 SUSD one-off · no wallet required
Abstract
This paper focuses on the influence of detailed engineering maturities on offshore engineering, procurement, and construction (EPC) project procurement and construction cost performance. The authors propose a detailed engineering completion rating index system (DECRIS) to estimate the engineering maturities, from contract award to beginning of construction or steel cutting. The DECRIS is supplemented in this study with an artificial neural network methodology (ANN) to forecast procurement and construction cost performances. The study shows that R2 and mean error values using ANN functions are 20.2% higher and 19.7% lower, respectively, than cost performance estimations using linear regressions. The DECRIS cutoff score at each gate and DECRIS forecasting performance of total cost impact were validated through the results of fifteen historical offshore EPC South Korean mega-projects, which contain over 300 procurement cost performance data points in total. Finally, based on the DECRIS and ANN findings and a trade-off optimization using a Monte-Carlo simulation with a genetic algorithm, the authors propose a cost mitigation plan for potential project risks based on optimizing the engineering resources. This research aids both owners and EPC contractors to mitigate cost overrun risks, which could be continuously monitored at the key engineering gates, and engineering resources could be adjusted per optimization results.
Reference Key
kim2019aenergies Use this key to autocite in the manuscript while using SciMatic Manuscript Manager or Thesis Manager
Authors Kim, Myung-Hun;Lee, Eul-Bum;
Journal energies
Year 2019
DOI
DOI not found
URL
Keywords

Citations

No citations found. To add a citation, contact the admin at info@scimatic.org

No comments yet. Be the first to comment on this article.